Tioga Storage – 60 day storage with injection and withdrawal ratchets
Maximum Daily Withdrawal Quantity (MDWQ) – Up to 184,000 Dth
Maximum Daily Injection Quantity (MDIQ) – Up to 61,333 Dth
Maximum Storage Quantity (MSQ) – Up to 11,040,000 Dth
Receipt Points for Injection – Tioga County, Pennsylvania via
Dominion meter number 90008 (primary)
Tennessee meter number 420253 (primary)
Tennessee meter number 420213 (primary – limited capacity)
Delivery Point for Withdrawal – Tioga County, Pennsylvania via
Dominion meter number 90008 (primary)
UGI – Central Penn Gas distribution system (primary)
Injection Ratchets
100% of MDIQ when inventory is less than 50% of MSQ
84% of MDIQ when inventory is 50% or more of MSQ
Withdrawal Ratchets
100% of MDWQ when inventory is 25% or more of MSQ
50% of MDWQ when inventory is less than 25% of MSQ
Contract Term – 1 April 2018 through 31 March – single or multiple year bids accepted
Fuel Reimbursement – less than or equal to 1%, assessed on all injections and wheeling
Commodity Charge – Applicable ACA on withdrawals
Demand Charge – Expressed as $X.XX per Dth of MSQ
Note: Any bid awarded with an MSQ less than the maximum listed above will have an MDWQ and an MDIQ proportional to the ratios of the maximums listed above.
Meeker Storage – 100 day storage with injection and withdrawal ratchets
Maximum Daily Withdrawal Quantity (MDWQ) – Up to 30,000 Dth
Maximum Daily Injection Quantity (MDIQ) – Up to 16,667 Dth
Maximum Storage Quantity (MSQ) – Up to 3,000,000 Dth
Receipt Points for Injection – Tioga County, Pennsylvania via
Dominion meter number 90008 (primary)
Tennessee meter number 420253 (primary)
Tennessee meter number 420213 (primary – limited capacity)
Delivery Point for Withdrawal – Tioga County, Pennsylvania via
Dominion meter number 90008 (primary)
UGI – Central Penn Gas distribution system (primary)
Injection Ratchets
100% of MDIQ when inventory is less than 50% of MSQ
84% of MDIQ when inventory is 50% or more of MSQ
Withdrawal Ratchets
100% of MDWQ when inventory is 25% or more of MSQ
50% of MDWQ when inventory is less than 25% of MSQ
Contract Term – 1 April 2018 through 31 March – single or multiple year bids accepted
Fuel Reimbursement – less than or equal to 1%, assessed on all injections and wheeling
Commodity Charge – Applicable ACA on withdrawals
Demand Charge – Expressed as $X.XX per Dth of MSQ
Note: Any bid awarded with an MSQ less than the maximum listed above will have an MDWQ and an MDIQ proportional to the ratios of the maximums listed above.
Wharton Storage – 100 day storage without injection and withdrawal ratchets
Maximum Daily Withdrawal Quantity (MDWQ) – Up to 10,000 Dth
Maximum Daily Injection Quantity (MDIQ) – Up to 10,000 Dth
Maximum Storage Quantity (MSQ) – Up to 1,000,000 Dth
Receipt Points for Injection – Wharton Storage near Leidy, Pennsylvania via
Transco meter number 1006326 (primary)
Delivery Point for Withdrawal – Wharton Storage near Leidy, Pennsylvania via
Transco meter number 1006326 (primary)
UGI – Central Penn Gas distribution system (primary)
Contract Term – 1 April 2018 through 31 March – single or multiple year bids accepted
Fuel Reimbursement – less than or equal to 1%, assessed on all injections and wheeling
Commodity Charge – Applicable ACA on withdrawals
Demand Charge – Expressed as $X.XX per Dth of MSQ
Note: Any bid awarded with an MSQ less than the maximum listed above will have an MDWQ and an MDIQ proportional to the ratios of the maximums listed above.